Yarra Ranges Civic Centre – May Update

By Community

Check out our latest update on the $26M Yarra Ranges Council Civic Centre Redevelopment.

So far in 2021, we have seen the suspended concrete slabs poured on Level 1 and structural steel installed to the new building. Roof works over the existing building and feature precast panels to the North, East and West sides of the new building are also in progress.

Internal works to be commenced over the coming weeks. Watch this space for further updates!

https://lnkd.in/g6USqch

Midfield Meat International

By Industrial

Johns Lyng Commercial Builders have been progressively working through the raw materials basement construction into the sub-structure and super structure works at this 10 million-dollar development for Midfield Meat International.

Moving forward, we will be looking to install the roof and fit out the building services to have the facility ready to commence commissions late April/ Early May.

Have a read of the below to find out more about what the Protein Plant will achieve for both the environment and the future of Warrnambool once completed!